Modular Building
Construction Stops on B2 BKLYN
The residential tower by SHoP Architects would set a precedent in modular construction technology.
-
Credit: SHoP ArchitectsB2 BKLYN, the 32-story tower designed by SHoP Architects was scheduled to be the first of three residential towers on the Pacific Park Brooklyn site formerly known as Atlantic Yards.
Credit: SHoP Architects
B2
BKLYN, the 32-story tower designed by SHoP Architects was scheduled to
be the first of three residential towers on the Pacific Park Brooklyn
site formerly known as Atlantic Yards.
Among the many wrinkles in the saga of Atlantic Yards complex (now known as Pacific Park Brooklyn)—the controversial 22-acre mega-redevelopment of the area around the old Long Island Railroad terminal in Prospect Heights, Brooklyn—has been the absence of any actual housing to date. As is typical for almost all urban renewal projects, new at-market and low-income residences were naturally a central feature of the scheme from project developer Forest City Ratner Cos. (FCR) when it first garnered public approval—and public funds—in 2006 (Atlantic Yards B2 Owner is the single-purpose entity formed by FCR and its affiliates for the project according to a Bloomberg article). The Barclays Center sports and entertainment arena—the glitzy marquee component of the master plan originally devised by architect Frank Gehry, FAIA, and ultimately designed by SHoP Architects and AECOM—has been open since 2012. However, the arena’s immediate surrounds remain a desolate no man’s land, without a single new rental or condo property in evidence.
Apparently that’s going to remain the case for a while longer. On Aug. 27, project contractor Skanska USA Building (a New York–based business unit of parent company Skanska, based in Stockholm) halted all construction on B2 BKLYN, the first of three residential towers designed by SHoP to surround the sports arena and provide 1,500 units of mixed-income housing through landmark modular construction technology. Scheduled originally for completion in early 2014, B2 has only 10 stories of its ultimate 32 stories to show for almost two years’ work.

B2 is one of three towers on the site designed by SHoP Architects to be built using modular construction technology.
Credit: SHoP Architects
The 346,000-square-foot B2 BKLYN was to feature 363 apartments. But more exciting, at least for those in the building industry, was the potential use of modular construction technology, a process that FRC's filed complaint states that SHoP Architects and engineer Ove Arup & Partners developed in collaboration. Because modular construction hasn’t been completed at this building height before, the project first required the construction of a separate factory in which an estimated 60 percent of the residential modules' construction process would be completed off-site in environmentally controlled conditions. Skanska also won the contract to build the modular construction factory, which it did on the nearby Brooklyn Navy Yard.

B2 BKLYN under construction in May 2014.
Credit: AP / Mark Lennihan
As the Metabolists themselves demonstrated, however, modular construction for multi-unit housing has proven considerably more difficult in practice than in theory. The Nagakin Capsule Tower from designer Kisho Kurokawa, one of the movement’s banner projects, was none too well received on its 1972 debut and now has fallen into considerable disrepair.
The housing at Atlantic Yards was never projected to be anywhere near so ambitious, nor so architecturally avant-garde, as Nagakin. SHoP's simple glass-and-steel structures, with their mildly contextual façades, might as easily have been built using conventional methods. But FCR and Skanska saw an opportunity to have what one FCR representative referred to as an “iPhone moment,” a breakthrough demonstration of the economy and efficiency of the modular approach.
-
Credit: SHoP ArchitectsInterior rendering of one of the 363 modular apartment units.
Credit: SHoP Architects
Interior rendering of one of the 363 modular apartment units.
For Brooklyn, this latest setback is just one more in a long series of frustrations with the Atlantic Yards over the last eight years, one that leaves a giant hole in the middle of a promising neighborhood. But the greater disappointment, perhaps, is for advocates of modular building, an architectural mode that seems always on the cusp of greatness. FCR, perhaps predictably, remains bullish not just about the project, but about the prospects for modular in commercial development. In the aforementioned New York Times’ Aug. 28 article on B2’s shutdown, FCR president and CEO Mary Anne Gilmartin said, “This is not a referendum on modular, it’s a monetary dispute. We’re confident we’ll get the building built.” But whether modular construction is the route that FCR takes is far less certain.
*Update, Sept. 4, 2014, at 5:15 p.m. ET: Gilmartin sent the following letter to Skanska.
<p><em>Note: ARCHITECT will continue to report on the B2 BKLYN project status as more information becomes available.</em></p> </div></body></html>
*Update, Sept. 5, 2014, at 4:25 p.m. ET: When asked for comment, Skanska USA Building provided this statement from co-COO Richard Kennedy:
"By issuing this letter to the press prior to even sending it to its partner, Skanska Modular, Forest City has proven it is more interested in engaging in a propaganda exercise to take the public’s eye off the serious consequences of its failures at the B2 Project instead of simply fixing the commercial and design issues that led to the unfortunate need to shut-down the project and factory on August 27. As for the letter itself, it is completely devoid of substance and Skanska Modular will address it consistent with the parties’ partnership agreement. Again, Skanska remains hopeful commercial and economic sensibilities will prevail and that Forest City will resolve its problems at the B2 Project so we can get back to building and get the factory workers back to work. But, Skanska simply will not be coerced into surrendering its contractual rights by Forest City’s inappropriate tactics."
*Update, Sept. 5, 2014, at 5:32 p.m. ET: FCRC Modular has filed a complaint against Skanska Modular and Richard Kennedy.